💡 Bottom Line Up Front (BLUF): Premix Bag Requirement Table (100 sq ft)

For a standard 100 sq ft slab, the number of premix concrete bags required depends directly on slab thickness (4", 5", or 6"). Always add a 10% waste allowance for uneven sub-base excavation.

Slab Thickness Cubic Feet Volume Cubic Yards 80lb Bags (+10% Waste) 60lb Bags (+10% Waste)
4 Inches (Patio/Walkway)33.33 ft³1.23 yd³61 bags81 bags
5 Inches (Driveway/Shed)41.67 ft³1.54 yd³76 bags102 bags
6 Inches (Heavy Vehicle)50.00 ft³1.85 yd³92 bags122 bags

1. Rectangular Slab Calculation Formula

To calculate bags for a slab, multiply length by width by thickness (in feet) and divide by the bag yield ($0.60 \text{ ft}^3$ per 80lb bag).

Bags (80lb) = (Length_ft × Width_ft × Depth_in / 12) ÷ 0.60 × 1.10

For raw material batching with cement, sand, and gravel, refer to our Concrete Mix Ratios & Compaction Guide.

2. Cylindrical Post & Sonotube Footing Formula

For round post holes and cylindrical sonotube footings, calculate volume using $V = \pi r^2 h$.

A 12-inch diameter sonotube post hole dug 3 feet deep yields $1.57 \text{ ft}^3$ of volume, requiring 3 bags of 80lb premix concrete.